Uncertified application assessment timeframe:
- We allow 25 business days for the City to assess your application; and
- 21 calendar days for the applicant to provide further information if requested by the City.
Certified application assessment timeframe:
- We allow 10 business days for the City to assess your application; and
- 21 calendar days for the applicant to provide further information if requested by the City.
The Building Act allows for the Permit Authority to refuse an application if all required information is not provided within the 21 day period mentioned and the City can retain the application fee.
Notice of Completion
A notice of completion application is available on the Department of Mines, Industry Regulation and Safety website.
Building Occupancy Permit
A building occupancy permit application is available on the Department of Mines, Industry Regulation and Safety website.