Gilmore Avenue Shared Path Construction Stage 2 - Chisham Avenue to Wellard Road

StatusCommenced
Project TypesFederal Government Projects
Start November 2023
Finish April 2024
Budget N/A
Gilmore Avenue Shared Path Construction Stage 2 - Chisham Avenue to Wellard Road

The City recently awarded the construction of Stage 2 of the new 3m wide red asphalt shared path from Chisham Avenue to Wellard Road to Downer Group.

Works are currently scheduled to commence Monday 30 October 2023 and will continue until late April 2024.