Gilmore Ave (A), Leda

StatusPlanned
Project TypesState Government Projects
Start November 2024
Finish November 2024
Budget 129,010
Gilmore Ave (A), Leda

Scope of Work: Cracking pavement will be stabilized using foam bitumen to strengthen it and extend its life. Excess material will be removed from the site. A final wearing course of 40mm thick, 14mm stone with DGA (75 Marshall blow) will be applied.

Project Limits: The works will start 570m west of Runnymede Gate and end 680m west of Runnymede Gate, westbound.

Objective: To address cracking issues and improve the overall durability of the pavement.