Colchester Ave – Middleham Boulevard to Dunrobin Avenue:
A section of Colchester Avenue will undergo rehabilitation using form bitumen stabilisation and Asphalt to enhance pavement conditions. The City emphasizes pavement stabilisation to recycle existing road materials and reduce waste.
Task Name | Duration | Start | Finish |
Colchester Avenue - Pavement Rehabilitation | 4 days | Tue 28/11/23 | Fri 1/12/23 |
Stabilisation | 1 day | Tue 28/11/23 | Tue 28/11/23 |
Asphalt | 1 day | Fri 1/12/23 | Fri 1/12/23 |