Scope of Work: The 860m section of Barker Road, beginning at Braddock Road, has an ageing seal that has developed cracks and potholes. To restore the road’s condition and improve its longevity, the project will involve the following activities:
Overlay: The road section will be overlayed with a 30mm thick layer of 10mm stone Dense Graded Asphalt (DGA) to repair surface damage and extend the pavement's lifespan.
Kerb Replacement: Broken semi-mountable kerbs at the intersection will be replaced to ensure proper drainage and road safety.
Project Limits: The works will cover an 860m section of Barker Road, starting from Braddock Road.
Objective: To repair existing surface defects, enhance the road's durability, and improve safety and functionality within the specified section.